DTEK Grids repaired more than 9,200 km of power lines in order to prepare the grids for winter

Thermal power generation16 August 2024
During the first half of 2024, DTEK Grids DSO repaired almost 9,200 km of power lines of various voltage class and 3,300 power facilities: substations and distribution points of various voltage level. The works were carried out withing the framework of the repair and investment program. DSO also invested more than UAH 2.2 bln in upgrade of power facilities in the I half of the year.
DTEK Grids repaired more than 9,200 km of power lines in order to prepare the grids for winter

Despite the full-scale enemy aggression, the scheduled activities are conducted on a yearly basis to ensure stability of the grids during peak load in the autumn-winter period.  

In the times of war, the company is doing everything possible for Ukrainians to have heat and power supply in winter and continues investing in development and modernization of the grids, to prepare electrical equipment for winter in particular. Energy workers have already reconstructed 4 distribution points and modernized 17 substations. 

Due to application of schedules of stabilization shutdowns, power equipment is wearing out and failing faster, therefore the volume of required investments increases. 

“Before the heating season, DTEK Grids continues to invest in stability of the grids and develop them. In particular, during the first half of 2024, the total scope of investments within the framework of the investment program since the beginning of 2024 is more than UAH 2.2 bln. We plan to additionally invest over UAH 2.6 bln in development and upgrade of the energy infrastructure by the end of the year,” – noted Oleksandr Fomenko, CEO at DTEK Grids. 

Energy workers also continue replacing obsolete meters of the region’s residents, which service life is expiring. They are replaced with the “smart” meters. In particular, energy workers have already replaced 89,500 items in the first half of the year and plan to replace another 91,900 meters with the new ones by the end of the year. 

In order to ensure the most efficient preparation for the 2024-2025 heating season, DTEK Grids also urges service companies of the multi-appartement houses – housing offices, condominiums, managing companies – to inspect their equipment, conduct required maintenance and eliminate possible malfunctions. After all, according to statistics, people were left without electricity in their houses in 25% of cases on average due to emergencies in the local networks. 

03 December 2025
Thermal power generation Yesterday, energy workers of DTEK Odesa Grids restored electricity to almost 48,000 families, left without power supply after enemy attacks
03 December 2025
Thermal power generation Number of emergencies on the grids in the Kyiv region increased by 34% due to the schedules: energy workers ask residents of the region to use electrical appliances rationally
03 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored power supply to 30 settlements of the region
02 December 2025
Thermal power generation An updated weekly schedule of power shutdowns in the Kyiv region: time of shutdowns was shifted one hour
01 December 2025
Thermal power generation In November, energy workers of DTEK Kyiv Regional Grids restored electricity to more than 424,000 homes after enemy attacks
01 December 2025
Thermal power generation In November, energy workers of DTEK Odesa Grids restored power supply to almost 170,000 families
01 December 2025
Thermal power generation Light despite shelling: DTEK Dnipro Grids energy workers restored power supply to 664,000 families in November
01 December 2025
Thermal power generation In November, DTEK Grids DSO restored electricity to more than 3.5 million homes after the attacks
28 November 2025
Thermal power generation Restorations after the attacks: DTEK Dnipro Grids energy workers restored electricity to 18,700 families
27 November 2025
Thermal power generation Number of emergencies in the Dnipropetrovsk region increased 6 times due to the schedules: energy workers ask residents of the region for help