Thermal power generation06 February 2025
On February 4 and 5, DTEK Donetsk Grids specialists continued to repair lines and equipment, damaged by shelling, thus restoring electricity to homes of almost 4,000 families, de-energized due to enemy shelling. Specialists of the energy company commence repairs immediately once it becomes possible and the military provide permission for work performance.
DTEK Donetsk Grids managed to restore electricity to almost 4,000 homes over the course of two days

For the past two days, DTEK Donetsk Grids specialists continued to work despite all security challenges. During this time, they managed to restore electricity to 6 settlements, thus restoring power to 3,935 homes of residents of the Donetsk region. 

The situation in the Donetsk region remains extremely difficult. The enemy continues to destroy peaceful towns and villages, including the energy infrastructure. According to the head of the region Vadym Filashkin, the enemy shelled settlements of the Donetsk region 14 times yesterday. 

DTEK Donetsk Grids specialists continue repairs once the situation and the military allow and have been working non-stop for 1,079 days now. Energy workers will definitely restore electricity to all residents of the region once they obtain permission for work performance from the Armed Forces of Ukraine. 

In case of a power outage, please inform us in any convenient way. To contact the company, please use official information channels only. DTEK Donetsk Grids specialists are ready to process your applications and answer all questions via remote service channels: DTEK Donetsk Grids website, company’s Facebook page. You can also contact the call center: +38 (063/096/099) 450 0 473, though it may take more time due to a large number of calls.  

Energy workers are working 24/7 and doing everything possible to provide electricity to every home. Only together and with joint efforts will we be able to endure and overcome these dark times! 

30 January 2026
Thermal power generation Over the course of two days, DTEK Dnipro Grids energy workers restored electricity to 53,600 families in the region
29 January 2026
Thermal power generation Why the voltage “surges” during Grids application of power shutdown schedules? – DTEK Dnipro answers
28 January 2026
Thermal power generation The heroes, who keep the lights on: energy workers of DTEK Dnipro Grids received awards from the President and from the city authorities of Dnipro
28 January 2026
Thermal power generation Energy workers of DTEK Grids DSO received state awards for electricity restoration
28 January 2026
Thermal power generation DTEK Dnipro Grids energy workers restored power to 39 settlements after enemy attacks
26 January 2026
Thermal power generation Over the course of the week, DTEK Dnipro Grids restored electricity to 120,000 homes in the Dnipropetrovsk region after the attacks
26 January 2026
Thermal power generation Over the course of the week, DTEK Grids DSO restored electricity to more than 1.2 million homes in the city of Kyiv and in Odesa, Dnipropetrovsk, Donetsk and Kyiv regions
23 January 2026
Thermal power generation Over the course of two days, DTEK Dnipro Grids energy workers restored electricity to 31,800 families in the region
22 January 2026
Thermal power generation Why can the power outage during application of shutdown schedules last over 7 hours? – DTEK Dnipro Grids answers
21 January 2026
Thermal power generation DTEK Dnipro Grids energy workers restored power to 57 settlements after rf’s attacks