DTEK Donetsk Grids repaired almost 270 kilometers of power grids to ensure stable power supply

Since the beginning of 2021, DTEK Donetsk Grids have repaired 268 km of power lines, 637 transformer substations, cleared 290 kilometers of routes under overhead lines. The company did this to reduce the number of failures and provide residents of the region with a stable and reliable power supply.
DTEK Donetsk Grids repaired almost 270 kilometers of power grids to ensure stable power supply

DTEK is transforming the business by introducing high-level standards of customer service. We are ugrading the networks and energy infrastructure of the region so that every customer has lights on and comfort at home. In 2021, we plan to repair 509 kilometers of power transmission lines, 464 transformer substations and distribution points, 193 high voltage substations. The company's energy workers have already completed about a half of the volume of work planned for the year,” says Oleksii Dehtyarev, CEO at DTEK Donetsk Grids.

Scheduled maintenances are the key to the stable functioning of the entire energy system in the region. The repair campaign provides for maintenance, regular repairs and overhaul of equipment, replacement, and restoration of old and worn-out network elements. In particular, repair, replacement or maintenance of transformers, switches, disconnectors, cable and overhead lines, electrical poles, pruning of trees under power lines, etc. Through such timely maintenances, there are fewer failures, and, therefore, there are fewer chances of power cuts at the customers' homes.

By the end of the year, DTEK Donetsk Grids will repair and maintain power transformers, transformer bushings, complex switchgears, and ventilation systems at 91 high-voltage substations.

There will be the following repairs completed on medium and low voltage networks:

  • 257 transformer substations and distribution points;
  • 308 km of air lines;
  • 5 km of cable lines;

Also, more than 40 kilometers of routes of overhead electrical networks will be cleared from bushes and overgrowth of trees. This means that these lines will become safer and more reliable.

10 December 2025
Thermal power generation DTEK Kyiv Grids relocated the overhead high-voltage grids for construction of the metro to Vynohradar
10 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored electricity to 61,000 families after russian attacks
08 December 2025
Thermal power generation Energy workers of DTEK Odesa Grids restored electricity to almost 214,000 families over the past week
08 December 2025
Thermal power generation Over the course of the week, DTEK Dnipro Grids restored electricity to 95,000 families after russian attacks
05 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored electricity to almost 12,000 homes after the attacks on power facilities
03 December 2025
Thermal power generation Yesterday, energy workers of DTEK Odesa Grids restored electricity to almost 48,000 families, left without power supply after enemy attacks
03 December 2025
Thermal power generation Number of emergencies on the grids in the Kyiv region increased by 34% due to the schedules: energy workers ask residents of the region to use electrical appliances rationally
03 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored power supply to 30 settlements of the region
02 December 2025
Thermal power generation An updated weekly schedule of power shutdowns in the Kyiv region: time of shutdowns was shifted one hour
01 December 2025
Thermal power generation In November, energy workers of DTEK Kyiv Regional Grids restored electricity to more than 424,000 homes after enemy attacks