some-alt
Main News Press Releases DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

Thermal power generation20 September 2023
DTEK energy workers installed a 14-ton transformer for powering of the new waterworks in the Dnipropetrovsk region that will provide water to the residents of the Kryvyi Rih district after demolition of the Kakhovka HPP. Replacement of equipment at the electric substation required two days, 8 crews and 7 additional items of DTEK Dnipro Grids machinery. During repairs, specialists used alternative power sources to maintain electricity for 1,500 residents.
DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

In late August, residents of the Dnipropetrovsk region that were affected by the demolition of Kakhovka HPP have received water from the main waterworks Inhulets-Pivdenne for the first time. In order to power it, DTEK Dnipro Grids energy workers had to promptly upgrade equipment and replace a transformer at the 35 kV substation. The existing transformer was replaced with a more powerful one that could ensure electricity supply to the pump station of the new waterworks. 

DTEK is a reliable partner of society and state. Realizing the need to urgently provide residents of the Dnipropetrovsk region with water, we concentrated all our efforts on prompt energization of the new waterworks. Currently, we have completed upgrade of the high-voltage substation, which will provide electricity to one part of the new waterworks. To solve this task, we have replaced a 2.5 MVA transformer with the one almost three times more powerful 6.3 MVA. This will help provide the waterworks with electricity required, and residents of the Kryvyi Rih district with long-awaited water, informed DTEK Dnipro Grids

A transformer weighing over 14 tons was delivered from Dnipro. Its installation required an auto crane. Mounting and setup of equipment at the substation was carried out by 4 crews of specialists.  

The replacement activities lasted two days. In order not to leave 1,500 residents of Shyroke and Novolativka communities without electricity during this period of time, DTEK Dnipro Grids has installed 10 generators of 30 to 140 kWt capacity. They were brought by the trucks from nine districts of the region. 17 specialists have been installing and connecting generators, energizing lines and 13 transformer substations turn by turn. 

Overall, the works involved 8 crews and 7 additional items of DTEK Dnipro Grids machinery. 

10 December 2025
Thermal power generation DTEK Kyiv Grids relocated the overhead high-voltage grids for construction of the metro to Vynohradar
10 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored electricity to 61,000 families after russian attacks
08 December 2025
Thermal power generation Energy workers of DTEK Odesa Grids restored electricity to almost 214,000 families over the past week
08 December 2025
Thermal power generation Over the course of the week, DTEK Dnipro Grids restored electricity to 95,000 families after russian attacks
05 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored electricity to almost 12,000 homes after the attacks on power facilities
03 December 2025
Thermal power generation Yesterday, energy workers of DTEK Odesa Grids restored electricity to almost 48,000 families, left without power supply after enemy attacks
03 December 2025
Thermal power generation Number of emergencies on the grids in the Kyiv region increased by 34% due to the schedules: energy workers ask residents of the region to use electrical appliances rationally
03 December 2025
Thermal power generation DTEK Dnipro Grids energy workers restored power supply to 30 settlements of the region
02 December 2025
Thermal power generation An updated weekly schedule of power shutdowns in the Kyiv region: time of shutdowns was shifted one hour
01 December 2025
Thermal power generation In November, energy workers of DTEK Kyiv Regional Grids restored electricity to more than 424,000 homes after enemy attacks