some-alt
Main News Press Releases Reliable power supply: Odessaoblenergo modernizes lines and equipment in Suvorovsky District

Reliable power supply: Odessaoblenergo modernizes lines and equipment in Suvorovsky District

Thermal power generation09 September 2020
Odessaoblenergo modernizes 110/10 kW substation called «Kryimskaya», and reconstructs 7 km of 10 kW cable lines to ensure that 42,000 clients and 2,268 enterprises in Suvorovsky District are provided with reliable and high-quality power supply.
Reliable power supply: Odessaoblenergo modernizes lines and equipment in Suvorovsky District

In early 2020, Odessaoblenergo began reconstruction of about 7 km of cable lines in the Kotovskoho residential area. Power engineers are modernizing three cable lines that come from the Kryimskaya substation and lead to the following 10 kW distribution units: “Zvezdnyiy” (31 Marselskaya Str.), “Dneprovskiy” (78 Geroev oboronyi Odessyi Str.), and “Dobrovolskiy” (2 Bocharova Str.).

“DTEK is a reliable partner of the community. The substation and power grids reconstruction is part of the modernization program of the power equipment in Odessa, which our company implements consistently. This year, in accordance with our Investment Program, we are investing more than UAH 34 million in upgrading the power equipment in Suvorovsky District”, says Aleksandr Fomenko, Odessaoblenergo Director General.

The company’s specialists are replacing old cables with the new ones made of cross-linked polyethylene. These cables have a larger cross-section of 300 to 800 sq.m, and they are more reliable. In case of emergency outages, the power engineers can quickly restore power supply to clients both from the backup lines and from other distribution units. This will ensure that residents within Zabolotnoho, Paustovskoho, Marselskaya and Bocharova streets are provided with high-quality power supply.

Cable lines reconstruction is one of the important steps in modernization of the 110/10 kW Kryimskaya substation (22/1 Ak. Zabolotnoho Str.), which feeds more than 45,000 consumers of Suvorovsky District. In 2020, the power engineers installed two new transformers with a larger capacity of 63 MVA instead of the old 40 MVA, four new environmental vacuum switches. They are now proceeding with construction work and installation of 110 kV equipment. The work is scheduled to be completed in 2021
Also, in the first six months, within the Investment Program framework, the power engineers installed the new 10/0.4 kV unloading substation with 250 kVA transformers in the village of Shevchenko in Suvorovsky District. The plan is to install another similar one by the end of the year. In addition, specialists will separate 3 km of wire and replace it with an aerial bundled line cable. This will provide 1210 consumers with high quality and stable voltage.

14 January 2026
Thermal power generation Energy workers are building a temporary power circuit for the left bank of Dnipro
12 January 2026
Thermal power generation Massive strikes on the energy sector: DTEK Dnipro Grids restored electricity to 1.1 mln families over the course of the week
12 January 2026
Thermal power generation Electricity restored to more than 2 million families: a new DTEK Grids DSO anti-record for restorations after enemy attacks
09 January 2026
Thermal power generation DTEK Dnipro Grids energy workers restored electricity to more than 1 million homes after the rf’s large-scale attack
07 January 2026
Thermal power generation Why were there more light on the New Year holidays then now? – DTEK Dnipro Grids explains
07 January 2026
Thermal power generation One of the DTEK Dnipro Grids units was damaged by the night Shahed attack
05 January 2026
Thermal power generation Light despite the attacks: DTEK Dnipro Grids energy workers restored power supply to 595,000 families in December
05 January 2026
Thermal power generation In December, energy workers of DTEK Kyiv Regional Grids restored electricity to almost 400,000 homes after enemy attacks
02 January 2026
Thermal power generation Despite the attacks: energy workers of DTEK Dnipro Grids restored electricity to 38,000 homes in the region over 4 days of New Year festivities
30 December 2025
Thermal power generation DTEK Grids DSO restored electricity to more than 1.8 million homes in the capital and four regions over the course of the week