Main News Press Releases Reconstruction of Gostomel 110/10 kV substation is ongoing: DTEK Kyiv Regional Grids to complete 70% of the scheduled works

Reconstruction of Gostomel 110/10 kV substation is ongoing: DTEK Kyiv Regional Grids to complete 70% of the scheduled works

Reconstruction of 110/10 kV Gostomel substation, which is one of the busiest transformer substations in the Kyiv region, is ongoing. Since the project was launched in 2020, DTEK Kyiv Regional Grids has completed more than 70% of all planned works. In October this year, the substation will provide an additional 34 MW of capacity for the company's customers in Gostomel and its surrounding areas. In general, the reconstructed substation will be able to supply up to 50 MW of electricity to the grid.
Reconstruction of Gostomel 110/10 kV substation is ongoing: DTEK Kyiv Regional Grids to complete 70% of the scheduled works

DTEK Kyiv Regional Grids continues reconstruction of 110/10 kV Gostomel substation per the schedule. The company has already invested over UAH 50 million in the project and completed 70% of all planned works. The total cost of the project is UAH 108 million. The equipment will be tested and setup in September this year, and from October the substation will be fully operational.

"DTEK is a reliable and conscious company that cares about the future of Ukraine. The Gostomel substation is an indispensable facility for the stable energy supply of more than 9,000 DTEK customers. Kyiv regional networks important infrastructure facilities - Antonov International Airport and Vetropack glass plant. The additional capacity in this region will contribute to the social and economic development of the community,” says Vitalii Shayda, General Director of DTEK Kyiv Regional Grids.

At the 110/10 kV Gostomel substation, the company replaced 110 kV portable current transformers, built distribution and general substation control points. The installation of two new 110/10 kV power transformers with a capacity of 25 MW each and 110 kV SF6 circuit breakers is currently being completed. To prevent oil spills and entering the soil, a new oil collector is being built and its oil receivers are being reconstructed. The next step is the installation of four arc-quenching reactors, reconstruction of relay protection, remote control, etc.

Thanks to the reconstruction, the substation equipment will be working in normal operation. After all, the old power transformers built in 1982 are working at the limit of their capabilities. They cannot guarantee the stability of energy supply in the region, which doubled in the last 8 years to 20 MW. If one of the transformers is disconnected, the load on the other can increase by more than 150% and the protective automation will cause power cuts to some customers. If the second transformer is disconnected during the emergency repair, the whole area supplied by the 110/10 kV substation Gostomel will be left without power.

When the reconstruction is complete, up to 60% of the backup transformer capacity will be available at the Gostomel power center, which will ensure a stable energy supply to the company’s customers, the possibility of connecting new and increasing the capacity of existing facilities.

You can see how the reconstruction of the Gostomel substation is going on here.

As previously reported, DTEK Kyiv Regional Grids will earmark UAH 614 million to upgrade the Kyiv region's electricity infrastructure in 2021.

26 November 2024
Thermal power generation Russians attacked DTEK Dnipro Grids energy workers’ vehicle during performance of repairs
26 November 2024
Thermal power generation Development in compliance with the sustainable development principles remains our key goal, despite the challenges of war, – DTEK Grids
26 November 2024
Thermal power generation Last week, DTEK Donetsk Grids restored electricity to 47,900 homes, de-energized due to bad weather and shelling
25 November 2024
Thermal power generation DTEK energy workers restored power supply after shelling to more than 20,000 homes in the Dnipropetrovsk region over the course of a week
25 November 2024
Thermal power generation DTEK restored electricity to more than 357,000 families in Odesa, Dnipropetrovsk and Donetsk regions over the course of a week
24 November 2024
Thermal power generation DTEK Dnipro Grids restored electricity to 4,800 families after shelling
23 November 2024
Thermal power generation DTEK Donetsk Grids restored electricity to 9,800 homes yesterday
22 November 2024
Thermal power generation Consequences of bad weather and shelling: DTEK energy workers restored electricity to almost 105,000 homes in the Dnipropetrovsk region yesterday
22 November 2024
Thermal power generation Yesterday, DTEK Donetsk Grids restored electricity to 17,400 homes after hurricane and shelling
21 November 2024
Thermal power generation DTEK energy workers restored electricity to almost 3,500 homes in the Dnipropetrovsk region after shelling