37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times

Thermal power generation13 August 2026
In the first half of 2026, DTEK Grids Distribution System Operators reconstructed 7 transformer points and 17 substations, as well as built 13 new transformer points in the city of Kyiv and in Kyiv, Dnipropetrovsk, and Odesa regions. This is 1.5 times more than during the similar period last year. Energy workers continue to upgrade the energy infrastructure and prepare the grids for operation in the conditions of peak loads, during the autumn-winter period in particular.
37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times

The volume of an investment program is annually approved by the state regulator NEURC for all Distribution Systems Operators. In parallel, DTEK Grids DSO repaired almost 2,000 km of overhead lines, 4,600 cable lines and almost 3,000 power facilities over the first half of 2026.

In order to reduce the risks of emergencies and ensure reliability of power supply to the families, specialists cleared 5,000 km of the overhead line routes from trees and brushwood.

“We continue to systematically upgrade the grids and improve their sustainability. Over the first half of the year, we increased the volumes of reconstruction and new construction of power facilities by 1.5 times in comparison to the previous year. In 2026, we plan to invest a total of more than UAH 6.7 bln in the upgrade of the grids. This will allow us to create a safety margin for the future heating season,” — noted DTEK Grids CEO Alina Bondarenko.

Repair and investment programs of DTEK Grids DSO are directed at improving reliability of power supply to the customers and preparing the girds for operation in the conditions of peak loads. At the same time, further development and modernization of the infrastructure create the required technical capacities for connection of new customers.

12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration
29 July 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids unit in the Dnipropetrovsk region with a fibre optic drone
28 July 2026
Thermal power generation A third more: DTEK Grids DSO installed 136,000 smart meters over six months
27 July 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 650,000 families in four regions over the course of the week