DTEK Odesa Grids completed main items of the repair program to stably go through the winter

Thermal power generation05 November 2025
DTEK Odesa Grids completed main items of the repair program to stably go through the 2025/2026 heating season. The company repaired over 2,000 km of the overhead lines and over 1,000 items of cable lines, upgraded 676 power facilities and cleared over 1,800 km of lines from branches and drywood. This will allow to increase reliability of power supply for the residents of the Odesa region in the conditions of winter load.
DTEK Odesa Grids completed main items of the repair program to stably go through the winter

Energy workers are systematically preparing the grids for winterSince the beginning of 2025, specialists have already repaired over 2,000 km of the overhead lines, 1,000 items of cable linesreplaced almost 600 poles and carried out major overhaul of 676 power facilitiesIn order to prevent power outages due to bad weatherenergy workers have also cleared 1,800 km of the overhead lines from tree branches and drywoodEquipment repairs and modernization allow improving stability of the gridreducing number of emergencies during bad weather in particular. 

“Energy workers are preparing the grids for winter throughout the yearOver the first nine monthswe have already spent more than UAH 140 mln on implementation of the repair programThe total sum of investments this year amounts to UAH 210 mlnWe are doing everything possible to ensure stable power supply in winterproviding there will be no new enemy attacks on the region’s energy infrastructure,” – commented Dmytro HryhorievCEO at DTEK Odesa Grids. 

By the end of the yearspecialists plan to repair another 135 km of the overhead linesperform major overhaul of 191 power facilities and clear 518 km of the overhead line routes from branches and drywood. 

In addition, to prepare for the winter period as efficiently as possible, the company urges housing service organizations – municipal housing offices, condominium associations, housing cooperatives, and managing companies – to check the condition and perform maintenance of their in-building electrical networks and eliminate possible malfunctions in time. After all, the statistics shows that an average of 30% of emergencies happen in the in-building or adjacent networks, which are not maintained by the Distribution System Operator. 

As informed earlierDTEK Odesa Grids has already invested over UAH 764 mln in renewal and modernization of the energy infrastructure of the Odesa region in 2025 within the framework of its own investment programAdditionallyan emergency stock of materials and equipment worth over UAH 100 mln was formed to promptly react to any emergency. 

25 February 2026
Thermal power generation Over the course of two days, DTEK Dnipro Grids energy workers restored power to 7,000 families in the region after rf’s attacks
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Odesa Grids restored electricity to every home more than 5 times over the 4 years of war
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Donetsk Grids repaired almost 30,000 km of power lines over the course of 4 years
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Kyiv Regional Grids repaired more than 2,000 power lines over the course of 4 years
24 February 2026
Thermal power generation The light stands: energy workers of DTEK Grids DSO repaired more than 30,000 km of power lines over the course of 4 years
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Dnipro Grids repaired almost 9,700 km of power lines over the course of 4 years
23 February 2026
Thermal power generation Over the course of the day, energy workers of DTEK Kyiv Regional Grids restored power to almost 6,000 families in the Kyiv region after enemy attacks
20 February 2026
Thermal power generation DTEK Dnipro Grids restored electricity to 105 settlements after russian attacks
20 February 2026
Thermal power generation Why the voltage “surges” during application of power shutdown schedules? – DTEK Kyiv Regional Grids answers
19 February 2026
Thermal power generation Energy workers of DTEK Dnipro Grids are removing icing and repairing broken wires: electricity has already been restored to more than 5,000 homes