Energy workers are building a temporary power circuit for the left bank of Dnipro

Thermal power generation14 January 2026
Energy workers of DTEK Dnipro Grids are working non-stop to restore electricity to the residents of the left bank of Dnipro as soon as possible. The situation in the region remains difficult, however, specialists are now completing construction of a stand-alone temporary power circuit. It is planned to provide electricity by the end of the day.
Energy workers are building a temporary power circuit for the left bank of Dnipro

The attack that took place on the night from Friday to Saturday caused significant damage to the power facilityIts complete restoration requires timeIn order to ensure that families have electricity during the repairsenergy workers have been forced to build a temporary power circuit. 

We are doing everything to energize the left bank of DniproWe have been working for five days nowUnfortunatelythe scale of destruction does not currently allow to overhaul the power supply system in these districtsThereforewe are building a temporary power circuit to promptly provide electricity to the homesUnfortunatelythis circuit is less resistant to overloadsPower surges or failures in the general energy system may lead to emergencies fasterThis is what happened yesterdayOur specialists plan to finalize the circuit and reenergize the left-bank district of the city by the end of the day,” – underscored Anton Dralovhead of the high-voltage grids operation department at DTEK Dnipro Grids. 

Energy workers are working 24/7 – despite air raid alertssnow and frost. 

We ask residents to help preserve electricity: 

  • do not turn on power appliances (kettlesboilersheaters) immediately after electricity restorationwait for up to 30 minutes; 
  • turn on electrical appliances in turns. 

We understand how hard it is without electricityWe are working 24/7 and are doing everything possible and often impossible to restore electricity to every home 

25 February 2026
Thermal power generation Over the course of two days, DTEK Dnipro Grids energy workers restored power to 7,000 families in the region after rf’s attacks
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Odesa Grids restored electricity to every home more than 5 times over the 4 years of war
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Donetsk Grids repaired almost 30,000 km of power lines over the course of 4 years
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Kyiv Regional Grids repaired more than 2,000 power lines over the course of 4 years
24 February 2026
Thermal power generation The light stands: energy workers of DTEK Grids DSO repaired more than 30,000 km of power lines over the course of 4 years
24 February 2026
Thermal power generation The light stays on: energy workers of DTEK Dnipro Grids repaired almost 9,700 km of power lines over the course of 4 years
23 February 2026
Thermal power generation Over the course of the day, energy workers of DTEK Kyiv Regional Grids restored power to almost 6,000 families in the Kyiv region after enemy attacks
20 February 2026
Thermal power generation DTEK Dnipro Grids restored electricity to 105 settlements after russian attacks
20 February 2026
Thermal power generation Why the voltage “surges” during application of power shutdown schedules? – DTEK Kyiv Regional Grids answers
19 February 2026
Thermal power generation Energy workers of DTEK Dnipro Grids are removing icing and repairing broken wires: electricity has already been restored to more than 5,000 homes