some-alt
Main News Press Releases DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

Thermal power generation20 September 2023
DTEK energy workers installed a 14-ton transformer for powering of the new waterworks in the Dnipropetrovsk region that will provide water to the residents of the Kryvyi Rih district after demolition of the Kakhovka HPP. Replacement of equipment at the electric substation required two days, 8 crews and 7 additional items of DTEK Dnipro Grids machinery. During repairs, specialists used alternative power sources to maintain electricity for 1,500 residents.
DTEK Dnipro Grids energy workers ensured electricity supply to the new waterworks after the demolition of Kakhovka HPP

In late August, residents of the Dnipropetrovsk region that were affected by the demolition of Kakhovka HPP have received water from the main waterworks Inhulets-Pivdenne for the first time. In order to power it, DTEK Dnipro Grids energy workers had to promptly upgrade equipment and replace a transformer at the 35 kV substation. The existing transformer was replaced with a more powerful one that could ensure electricity supply to the pump station of the new waterworks. 

DTEK is a reliable partner of society and state. Realizing the need to urgently provide residents of the Dnipropetrovsk region with water, we concentrated all our efforts on prompt energization of the new waterworks. Currently, we have completed upgrade of the high-voltage substation, which will provide electricity to one part of the new waterworks. To solve this task, we have replaced a 2.5 MVA transformer with the one almost three times more powerful 6.3 MVA. This will help provide the waterworks with electricity required, and residents of the Kryvyi Rih district with long-awaited water, informed DTEK Dnipro Grids

A transformer weighing over 14 tons was delivered from Dnipro. Its installation required an auto crane. Mounting and setup of equipment at the substation was carried out by 4 crews of specialists.  

The replacement activities lasted two days. In order not to leave 1,500 residents of Shyroke and Novolativka communities without electricity during this period of time, DTEK Dnipro Grids has installed 10 generators of 30 to 140 kWt capacity. They were brought by the trucks from nine districts of the region. 17 specialists have been installing and connecting generators, energizing lines and 13 transformer substations turn by turn. 

Overall, the works involved 8 crews and 7 additional items of DTEK Dnipro Grids machinery. 

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration