Energy workers of DTEK Odesa Grids helped restore operation of the high-voltage substation that provides Khersonians with water and heating

Thermal power generation06 February 2024
During December 2023 and January 2024, energy workers of DTEK Odesa Grids helped repair electrical infrastructure in the Kherson region, damaged by the enemy, on four occasions. Specialists managed to restore operation of the 150 kV high-voltage substation to energize critical infrastructure facilities in the first place and provide Khersonians with heat and water supply.
Energy workers of DTEK Odesa Grids helped restore operation of the high-voltage substation that provides Khersonians with water and heating

10 energy workers and 3 items of machinery of DTEK Odesa Grids went to help with emergency and restoration activities in the Kherson region. These are the crews of the industrial vehicles and high-voltage grids operation department. 

“Over the past two months, our men went to Kherson on four occasions to help colleagues put a 150 kV high-voltage substation into operation. Transformers went out of order due to enemy shelling back in December. Let me remind that last summer this very substation was flooded due to the destruction of Kakhovka HPP by the invaders. Every time we help our colleagues-energy workers repair equipment to energize critical infrastructure facilities in the first place and provide Khersonians with heat and water supply,” – underscored Dmytro Hryhoriev, CEO at DTEK Odesa Grids. 

Energy workers have been working in the extremely difficult conditions to the sounds of explosions as the enemy continues to shell Kherson from the left bank of the Dnipro river. For security reasons, they worked only in bulletproof vests and hardhats. Specialists have repaired a power facility to the operating state and put a substation into operation, thus restoring water and heat supply to the homes of Khersonians. 

“When we went to Kherson with the boys, there was no fear. It was scary to see people's eyes that look at you with despair and hope. Khersonians lived in occupation for eight months and now they suffer from daily enemy shelling. We simply had no choice but to repair the substation. As we cannot even imagine what it is like to be without heating, electricity and water in winter. But they, unfortunately, know it from their own bitter experience,” Andrii Zhosan, head of the electrotechnical laboratory at DTEK Odesa Grids shared his emotions 

Let us remind that in August 2023, the Minister of Energy of Ukraine Herman Halushchenko and the head of Odesa RMA Oleh Kiper awarded four energy workers of DTEK Odesa Grids with the Certificate of the Ministry of Energy of Ukraine and the breast badge “For excellence in energy industry”. Departmental awards were given for courage during restoration of power supply in the Kherson region and for personal contribution to provision of Ukrainians with electricity during the war.  

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration