some-alt
Main News Press Releases Energy workers of DTEK Grids DSO are mastering the live repairs technique (without power shutdowns for the customers): 16,000 such works have been performed in 2023

Energy workers of DTEK Grids DSO are mastering the live repairs technique (without power shutdowns for the customers): 16,000 such works have been performed in 2023

Thermal power generation26 January 2024
Despite the war, DTEK Grids Distribution System Operators continue to create infrastructure for rebuilding of Ukraine and recovery of the economy. Energy workers of the company develop smart grids to be used as a foundation for resurrection of Ukrainian cities – new, modern, “smart”, and change approaches to work. In order to be able to conduct scheduled and emergency repairs in the nearest future without shutting down power for the customers, DTEK Grids DSO are mastering the method of live works. In 2023, energy workers conducted 16,012 repairs on the lines without de-energization of customers in Dnipropetrovsk, Odesa, Kyiv regions and in the capital.
Energy workers of DTEK Grids DSO are mastering the live repairs technique (without power shutdowns for the customers): 16,000 such works have been performed in 2023

DTEK Grids energy workers constantly improve methods of works on the grids. Since 2018, they started mastering technology of repairs without power shutdown. The goal is to conduct the majority of repairs in the nearest future without de-energization of customers.

“In 2022, we had to suspend our energy workers’ training for live repairs, as all resources were directed to repair of the electrical infrastructure after hostilities and restoration of electricity to homes of Ukrainians, - told Oleksandr Fomenko, CEO at DTEK Grids. – Now, we are gradually returning to the projects on development and application of modern technologies on the grids. Including, live repairs. However, in order for us to be able to train at the landfills in Ukraine and test personal protection equipment that allows performing such works, an outdated regulatory framework must change at the state level. As its inadaptability significantly increases the cost of application of this technology and this is an obstacle on the path of this project’s development.”

Depending on the difficulty of works, training of energy workers lasts from 3 days (works in meter cabinets) to 3 months (works on the 6-20 kV overhead lines) and is conducted at the special training landfills in Ukraine and Poland. From 2018 to 2022, live works method has been mastered by 1,079 energy workers of the DTEK Grids Distribution System Operators. The company has procured 86 sets of specials protective wear for these specialists: protective rubber gloves, hardhats, overalls, etc., as well as special insulated tools: dielectric mats, caps, covers, blankets, booms that protect electricians from electrocution during performance of live works on the lines.

In 2023, DTEK energy workers have conducted 16,012 repairs without power shutdown for the customers:

  • 9,917 repairs in the Dnipropetrovsk region;
  • 2,670 repairs in the Odesa region;
  • 1,633 repairs in Kyiv;
  • 1,792 repairs in the Kyiv region;

At the same time, DTEK Grids DSO constantly extend the list and difficulty of works. Currently, they conduct works not only on the low-voltage facilities, but also on the medium-voltage lines. Thus, in Kryvyi Rih in 2023, for example, was the first time that DTEK energy workers performed live works related to replacement of reinforced concrete poles on the 0.4 kV power lines. Previously, such works were conducted only with de-energization of consumers for a long period of time. Now, all works were conducted without any shutdowns.

DTKE Grids intends to further scale the project and increase the amount of live works, but to do that corresponding resources must be provided in the company’s investment program at the national regulator level and changes at the state level must start in the regulatory base that regulates training of energy workers and actual performance of such works on the grids.

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration