Preparing the Odesa region for the heat: energy workers repaired over 90 power facilities and 140 kilometers of the overhead lines

DTEK Odesa Grids completed almost 25% of its repair program to prepare the region for peak load seasons. In particular, it has already repaired over 90 substations of various voltage class. Despite the war, the company is doing everything necessary to ensure reliable operation of grids equipment and electricity supply to the homes of residents of Odesa region.
Preparing the Odesa region for the heat: energy workers repaired over 90 power facilities and 140 kilometers of the overhead lines

DTEK Odesa Grids specialists thoroughly monitor if equipment is operating correctly and if electricity is always available in the homes of residents of the Odesa region. Energy workers carry out inspections and diagnostics of equipment and power linesin particular, using the thermal viewers, mobile electrical laboratories, analysis of technical fluids, etc. Based on the received data, they determine weak spots, where an emergency may occur. 

In order to ensure stable operation of the city energy infrastructure during the peak consumption periods, period of hot weather or the autumn-winter period in particular, DTEK Odesa Grids specialists thoroughly prepare it: carry out required scheduled repairs. Currently, we have already completed almost 25% of the activities, scheduled for 2025. In particular, we have repaired 91 power facilities and almost 140 kilometers of the overhead lines. In 2025, the company will invest over 200 million hryvnias in the repair program,” commented Dmytro Hryhoriev, CEO at DTEK Odesa Grids. 

Overall, energy workers plan to upgrade 806 transformer substations and distribution points, repair 2,200 kilometers of the overhead lines, 370 transformers, 220 circuit breakers and 1,200 cable lines by the end of the year 

These activities will ensure reliable operation of equipment and minimize the risk of emergencies. Companys specialists are doing everything possible to ensure that the customers are always with electricity. 

As previously informed, despite the war and massive enemy attacks on the power facilities, residents of the Odesa region went through the heating season with electricity. This was achieved due to the systematic preparation for winter, automation of processes and coordinated work of DTEK Odesa Grids energy workers. The total sum of investments in repair and development of the grids amounts to almost UAH 1.3 bln. 

24 March 2026
Thermal power generation DTEK Grids DSO are speeding up installation of smart meters: more than third of all customers have already received it
23 March 2026
Thermal power generation DTEK Grids presented its experience in bird protection at the “Free Sky for Birds 2026” international conference
23 March 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 807,000 homes in four regions over the course of the week
20 March 2026
Thermal power generation Attacks on the power facilities: over the course of the day, DTEK Dnipro Grids energy workers restored electricity to 85 settlements in the region
18 March 2026
Thermal power generation 2025 Eco Summary of DTEK Kyiv Regional Grids: ISO 14001, decarbonization and responsible waste management
18 March 2026
Thermal power generation In the Dnipropetrovsk region, russians have once again attacked DTEK Dnipro Grids energy workers’ vehicle with drones
18 March 2026
Thermal power generation 2025 Eco Summary of DTEK Grids DSO: ISO 14001, decarbonization and over 2,000 tons of waste to recycling
17 March 2026
Thermal power generation Partners’ aid: DTEK Dnipro Grids received 4 transformers for restoration of energy equipment after the strikes
16 March 2026
Thermal power generation Restoring electricity after the strikes: energy workers of DTEK Kyiv Regional Grids restored power supply to more than 52,000 homes over the course of the week
16 March 2026
Thermal power generation Over the course of the week, DTEK Dnipro Grids restored electricity to 78,500 homes in the Dnipropetrovsk region after the attacks