Main News Press Releases Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities

Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities

Thermal power generation04 August 2026
In the first half of 2026, DTEK Grids Distribution Systems Operators repaired 240 substations, transformer and distribution points, damaged due to hostilities in the capital, and in Kyiv, Dnipropetrovsk, Odesa, and Donetsk regions. Energy workers are doing everything possible to restore electricity to the affected settlements as quickly as possible.
Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities

Energy workers commence work immediately after obtaining permission and access to the site of damage from AFU and SES. From January to June 2026, DTEK Grids DSO crews restored operation of 1,487 power lines with a total length of almost 6,000 km.

Since the beginning of 2026, the conducted work made it possible to restore power supply to a total of 14.5 mln* families in the city of Kyiv, and in Kyiv, Odesa, Dnipropetrovsk, and Donetsk regions.

“Despite constant attacks on the energy infrastructure, our energy workers are restoring the damaged grids on a daily basis. Since the beginning of the year, DTEK Grids DSO restored operation of 83% of the power lines that suffered destruction due to russian attacks. The crews are making extra efforts to restore electricity to Ukrainian families and business as quickly as possible,” — noted DTEK Grids CEO Alina Bondarenko.

DTEK Grids DSO specialists are often working in extremely difficult conditions, in the frontline regions, restoring electricity after hostilities. However, the pace of grids repairs is impacted by safety of conducting such works by the employees and by the scale of electrical equipment damage.

Energy workers are doing everything possible to provide electricity to every home.

*considering that some customers had electricity restored to them on two or more occasions.

03 September 2026
Thermal power generation Enemy drone attacked DTEK Dnipro Grids station in the Dnipropetrovsk region
02 September 2026
Thermal power generation Over the course of the day, energy workers of DTEK Kyiv Regional Grids restored electricity to more than 3,600 families after the attacks
01 September 2026
Thermal power generation Restoring electricity after the strikes: DTEK Grids DSO restored electricity to almost 4.5 mln homes in August
31 August 2026
Thermal power generation Three power facilities of DTEK Dnipro Grids attacked in the Dnipropetrovsk region
31 August 2026
Thermal power generation The President and the Cabinet of Ministers honoured six energy workers of DTEK Grids DSO for their contribution to the sustainability of the Ukrainian energy system
26 August 2026
Thermal power generation Storks settled in 88% of nests on protective platforms: DTEK Dnipro Grids summed up the results of monitoring
25 August 2026
Thermal power generation Over the course of the week, DTEK Grids DSO restored electricity to almost 600 settlements, de-energized by the attacks
21 August 2026
Thermal power generation 44 educational institutions and 475 students: how DTEK Grids DSO train future energy workers
17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids