Main News Press Releases Electricity restored to more than 2 million families: a new DTEK Grids DSO anti-record for restorations after enemy attacks

Electricity restored to more than 2 million families: a new DTEK Grids DSO anti-record for restorations after enemy attacks

Thermal power generation12 January 2026
From January 5 to 11, energy workers of the DTEK Grids Distribution Systems Operators (DSO) managed to completely or partially restore power to 881 settlements, de-energized by enemy strikes, thus restoring electricity to the homes of 2.1 mln families* in the capital and in Dnipropetrovsk, Donetsk, Odesa and Kyiv regions. Specialists of the DTEK Grids DSO repair the grids immediately after obtaining permission from the AFU and the SES.

The lion’s share was in the Dnipropetrovsk region, where the enemy attacked the energy sector multiple times over the course of the week, damaging a number of power facilities that transport electricity to the residents of Dnipro and Dnipropetrovsk region, and, thus, causing large-scale power outages throughout the region. Energy workers are working 24/7 to restore electricity as soon as possible. Over the course of the week, specialists here manage to restore power to 1.1 mln families. 

Thanks to the efforts of energy workers, electricity has been restored to 648,000 homes in the capital that were de-energized due to enemy attacks. 

At the same time, despite an extremely difficult situation in the Donetsk region caused by continuous fighting, region’s specialists managed to carry out a number of repairs and restore electricity to 115,700 homes. And though restoring power supply in the region becomes harder and harder, energy workers continue to restore power supply once it becomes possible.  

From January 5 to 11, energy workers also managed to restore electricity to homes of 106,700 local residents in the Odesa region, energy system of which continues to suffer from constant strikes. 

Last week, energy workers in the Kyiv region restored power to almost 92,000 homes that were also de-energized after enemy strikes. 

It should be noted that restorations were also significantly complicated by bad weather that raged throughout Ukraine last week. 

“The enemy continues to launch large-scale attacks on our country’s energy system. This week marked a new anti-record for restorations: colleagues restored electricity to 2.1 mln homes in the regions of our companies’ presence. Despite everything – large-scale destruction of the energy system, security challenges and fatigue - we continue to work and restore electricity for as long as 1,419 days now. Since the beginning of the full-scale invasion, we have already restored electricity to a total of over 35.5 mln* families in Kyiv, Dnipropetrovsk, Odesa and Donetsk regions, and in the city of Kyiv. We have restored electricity to some settlements close to the area of hostilities on dozens of occasions,” – noted Alina Bondarenko, CEO at DTEK Grids.  

DTEK Grids DSO energy workers are doing everything possible to eliminate damage as soon as possible. They commence work immediately after obtaining permission and access to the site of damage from the AFU and SES. 

considering that some customers had electricity restored to them on dozens of occasions. 

13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration
29 July 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids unit in the Dnipropetrovsk region with a fibre optic drone
28 July 2026
Thermal power generation A third more: DTEK Grids DSO installed 136,000 smart meters over six months