some-alt
Main News Press Releases DTEK Donetsk Grids restored electricity to 362,000 homes during the period of bad weather

DTEK Donetsk Grids restored electricity to 362,000 homes during the period of bad weather

Thermal power generation28 December 2023
December in the Donetsk region was marked by abnormal bad weather. It caused introduction of the regional-level emergency situation and led to large-scale damages of grids in the region. During the period of bad weather, DTEK Donetsk Grids specialists restored electricity to 482 settlements, thus restoring power to 362,000 homes (cumulative total, as some settlements were de-energized on multiple occasions). Meanwhile, energy workers kept restoring power supply that was damaged due to hostilities.
DTEK Donetsk Grids restored electricity to 362,000 homes during the period of bad weather

Abnormal weather conditions caused large-scale damages of grids in the Donetsk region due to ice and mass falling of the trees. Sleet and frost led to icing of everything in the Donetsk region. Trees could not withstand the weight of the ice cover and were falling down in large numbers, almost in every backyard, including falling on the power lines. Ice was so thick that, sometimes, lines with poles could not withstand its weight too. 197 high-voltage poles were damaged. There are lines, where more than 20 poles have collapsed. Therefore, some lines had to be practically rebuilt. 

Bad weather lasted long and came in several waves, thus lines that were just restored suffered damage again. Over the course of this ice chaos, specialists of the energy company have restored operation of 4,300 transformer substations, thus restoring power supply to 362,200 families in 482 settlements. 

The scale of damage and unstable weather conditions – from glaze ice to mud – also complicated restorations and required more time for repairs than usually. Energy workers are now completing restorations: building 5 power lines to replace the ones practically destroyed by bad weather. 4 of them are in Pokrovsk district. Another one is in Kramatorsk district. First, energy workers install poles, then they install steel structures and wire. Mud complicates work – machinery is skidding. Sometimes, energy workers have to work on claws, as aerial platforms cannot get in the fields. 

In order to facilitate repairs, energy workers of the Donetsk region got help from the crews from Dnipro, Odesa and Kyiv region. When restoration activities in the regions less affected by bad weather were completed, crews that worked there have also been relocated to the more affected regions. 

Energy workers continue to work in high alert mode to ensure that electricity is restored to every home. 

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration