Main News Press Releases Over the course of two days, DTEK Dnipro Grids energy workers restored power to 7,000 families in the region after rf’s attacks

Over the course of two days, DTEK Dnipro Grids energy workers restored power to 7,000 families in the region after rf’s attacks

Thermal power generation25 February 2026
On February 23 and 24, DTEK Dnipro Grids emergency crews restored power to 14 settlements in the Dnipropetrovsk region that were completely or partially de-energized due to the russian attacks. Despite the threats, specialists continue to repair the grids upon permission of the Armed Forces of Ukraine and SES. Our goal is to provide towns and villages with electricity, required for the normal life of the region’s residents.
Over the course of two days, DTEK Dnipro Grids energy workers restored power to 7,000 families in the region after rf’s attacks

DTEK Dnipro Grids specialists continue restoring electricity in the Dnipropetrovsk region after enemy strikes. Over the past two days, energy workers managed to restore operation of the grids in 14 settlements of the region, thus restoring electricity to homes of 7,018 families. 

Emergency crews commence work immediately after obtaining permission from the Armed Forces of Ukraine and the State Emergency Service. Despite constant danger and difficult security situationspecialists continue repairing damaged lines and equipment to provide towns and villages with electricity as soon as possible. 

Unfortunately, one energy worker was wounded during restoration activities in the frontline town on Tuesday. DTEK Dnipro Grids crew was supposed to restore power supply from the transformer substation, damaged by the strike. To do that, energy workers had to install a new pole in place of the destroyed one. When they approached a damaged pole, an enemy FPV drone hit nearby. The explosion resulted in the concrete structure injuring an electrician, who was promptly taken to the hospital. His condition is stable; paramedics are providing the necessary aid. 

Over 21,000 homes in the region currently remain without power supply. Restorations in the frontline zone are complicated by the security risks. Nevertheless, the works are ongoing. Energy workers make every effort to restore electricity to every home as soon as possible.  

In case of a power outage, please inform DTEK Dnipro Grids. To contact the company please use official information channels onlywebsitesocial mediaViber and Telegram chatbots. 

We are working 24/7 to ensure reliable power supply to houses and enterprises. 

13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration
29 July 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids unit in the Dnipropetrovsk region with a fibre optic drone
28 July 2026
Thermal power generation A third more: DTEK Grids DSO installed 136,000 smart meters over six months