some-alt
Main News Press Releases DTEK energy workers restored electricity to 56,000 homes, de-energized due to bad weather in the Dnipropetrovsk region

DTEK energy workers restored electricity to 56,000 homes, de-energized due to bad weather in the Dnipropetrovsk region

Thermal power generation07 August 2023
Consequences of yesterday’s bad weather in the Dnipropetrovsk region and emergencies that it caused continue to be eliminated. Yesterday, DTEK Dnipro Grids emergency crews have restored operation of most of the power lines and transformer substations, restoring electricity to 56,000 families in 100 settlements of the Dnipropetrovsk region. Repairs are ongoing.

On August 6, bad weather raged again in the Dnipropetrovsk region. A gale force wind with gusts up to 30 m/s caused widespread power outages. Nikopol, Synelnykove, Kryvyi Rih and Novomoskovsk districts were affected the most. 

A reinforced team of DTEK Dnipro Grids energy workers continues to eliminate consequences of bad weather. 30 crews of specialists were engaged in these works. Emergency repairs on lines and equipment are conducted immediately upon detection of new outages. The work is complicated by a large number of broken wires due to the fallen trees and corresponding blocking of access to the sites of emergencies.  

In 24 hours, from 13:00 on August 6 to 13:00 on August 7, DTEK energy workers managed to restore operation of more than 900 transformer substations and 58 power lines. Electricity has been restored to more than 56,000 families in 100 settlements that were completely or partially without electricity. 

All high and medium voltage lines have been repaired. Work on the 0.4 kV lines as per the specific customer requests are ongoing.  

Approximately 1,500 homes remain without electricity. Energy workers plan to complete all restoration activities by the end of the day today, providing weather conditions do not worsen. 

Distribution System Operator reminds of the following safety rules during bad weather

  • avoid power lines during strong wind;  
  • do not approach bare wires and broken lines, and never touch them; 

Please use any convenient way to inform about all emergencies in the grids: 

We are working 24/7 to ensure reliable power supply of houses and enterprises. 

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration