DTEK Kyiv Grids has restored electricity to 67,000 Kyivans over the course of a month

Thermal power generation06 October 2022
In September, DTEK Kyiv Grids specialists have eliminated 107 emergencies and restored power to homes of residents of the capital, left without electricity due to the damaged grids. The company continues to maintain proper technical condition of the city’s electrical infrastructure during wartime and prepare it for the peak load season.
DTEK Kyiv Grids has restored electricity to 67,000 Kyivans over the course of a month

In September, there were 107 power outages on the grid in Kyiv. The main cause was damage of cable lines due to excess of the permissible load or wear.

DTEK Group is a responsible business, partner of society and state. Thanks to the work of DTEK Kyiv Grids specialists, power has been restored to 67,000 company’s customers in Kyiv last month. Our specialists are working 24/7 to ensure stable operation of electrical infrastructure of the city and full scope of electricity supply to the capital,noted DTEK Kyiv Grids.

At the same time, the company continues its repair program related to preparation of the city for the autumn-winter season. 95% of scheduled activities are already completed. As informed earlier, as part of preparation of the capital for winter, DTEK Kyiv Grids will upgrade over 600 power facilities of the capital, repair 14 high-voltage substations and clear over 145 kilometers of the overhead power lines from green spaces, thus ensuring that tree branches do not cause damage of power lines when they, for example, fall on the wires during bad weather. Together, these measures will make it possible to improve reliability of power supply to residents, institutions and enterprises of the city during the increased electricity demand period.

At the same time, energy workers conduct joint training with rescue services of the capital to prepare for all challenges of the heating season in the conditions of martial law. DTEK Kyiv Grids also gave advices to condominiums and housing offices on how to prepare grids of multistoried buildings for winter, as serviceability of networks inside the multistoried buildings is one of the components of power supply reliability.

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities