some-alt
Main News Press Releases DTEK restored power to 1,645 families, left without electricity due to enemy shelling in the Dnipropetrovsk region

DTEK restored power to 1,645 families, left without electricity due to enemy shelling in the Dnipropetrovsk region

June 13 through 19, DTEK Dnipro Grids emergency and repair crews managed to perform repairs on equipment and lines in 12 settlements of the Dnipropetrovsk region, left without electricity due to hostilities, thus restoring service to homes of 1,645 families. DTEK Dnipro Grids specialists continue to perform restoration activities as soon as it becomes possible.
DTEK restored power to 1,645 families, left without electricity due to enemy shelling in the Dnipropetrovsk region

Last week, the enemy has frequently shelled settlements in Kryvyi Rih and Synelnykove districts. Novomoskovsk district of the Dnipropetrovsk region has also been hit by a missile strike. DTEK energy workers have been repairing damaged grids almost every day. Some homes require power restoration on multiple occasions due to frequent shelling and damage to electrical equipment. Works are conducted in coordination with the AFU and State Emergency Service. Over the course of the week, electricity was restored to 1,645 families in 12 settlements of the region.

As of June 20, operation of all lines, de-energized by enemy shelling, has been restored. There are no new outages.

If you have a power outage, please, inform DTEK Dnipro Grids. To contact the company, please, use official information channels only. Our specialists are ready to process your applications via remote service channels: website, social networks, contact center +38 (056/066/067/063) 790-99-00, 0-800-301-497, Viber and Telegram chatbot and Viber notification channel “ДТЕК info ДНЕМ”.

We are working 24/7 to ensure reliable power supply of houses and enterprises.

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration