Main News Press Releases For electricity in winter: DTEK will clear 1,700 kilometers of overhead lines from shrubs in Odesa and Odesa region by the end of 2022

For electricity in winter: DTEK will clear 1,700 kilometers of overhead lines from shrubs in Odesa and Odesa region by the end of 2022

Thermal power generation01 September 2022
Over the eight months of 2022, DTEK Odesa Grids has cleared 998 km of overhead lines’ routes from shrubs and deadwood. By the end of the year, it plans to prune branches along almost 800 more km. Company’s electricians are doing this to prepare Odesa region for the cold season. Pruning branches along overhead lines helps prevent power outages, caused by touching and falling of tree branches on the wires.
For electricity in winter: DTEK will clear 1,700 kilometers of overhead lines from shrubs in Odesa and Odesa region by the end of 2022

According to the Cabinet of Ministers, this heating season will be very difficult for Ukraine. All responsible parties should do the best they can to pass it. In order to reduce accidents rate and prepare grids in Odesa and Odesa region for the cold season, DTEK Odesa Grids will clear over 1,700 km of overhead lines from shrubs and branches in 2022. Over the eight months, energy workers have already cleared 998 km. By the end of 2022, specialists will prune deadwood along 775 km of 35-110 kV and 0.4-10 kV grids.

“DTEK Group is a responsible business, partner of society and state. The company is doing everything needed to ensure reliable operation of the electrical infrastructure of Odesa and Odesa region. Clearing routes of the overhead power lines is a part of this work. Our specialists have completed work on 103 kilometers of 35-110 kV lines and 895 kilometers of 0.4-10 kV lines. It will help avoid power outages due to fallen tree branches,” – noted the company.

In order to ensure safety of employees that prune trees, Distribution System Operator may temporarily de-energize the grids in accordance with schedules, approved by local authorities.

DTEK Odesa Grids notes that employees of the company should not be the only ones clearing routes from tree branches and undergrowth. According to the regulations, owners of green spaces and land users are the ones responsible for its preservation and proper care.

Residents of private sector should personally prune trees and shrubs on their territories and household plots. However, in order to ensure safety of such activities, they must be coordinated with schedules of temporary grid de-energization.

DTEK Odesa Grids specialists, in their turn, perform scheduled pruning of trees that grow in the security zone of overhead power lines.

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities