Main News Press Releases Over the course of a week, DTEK energy workers have restored electricity to 2,500 homes in the Dnipropetrovsk region, de-energized due to shelling

Over the course of a week, DTEK energy workers have restored electricity to 2,500 homes in the Dnipropetrovsk region, de-energized due to shelling

Thermal power generation14 November 2022
From November 7 to 13, DTEK Dnipro Grids emergency and restoration crews have restored electricity to homes of 2,500 families in 21 settlements of the Dnipropetrovsk region that were de-energized due to shelling. Our specialists commence work immediately after obtaining a permit from the AFU and SES. Our goal is to provide towns and villages with electricity, required for normal life of region’s residents.

Over the course of a week, the enemy continued to terrorize settlements in the south of the Dnipropetrovsk region. Despite constant threat from aggressor, DTEK Dnipro Grids specialists continue to promptly repair lines, damaged by shelling, and restore electricity to residents of the region.

Energy workers conduct work immediately after obtaining a permit from AFU and Emergency Service. Over the course of a week, power has been restored to 2,500 families in 21 settlements, completely or partially de-energized due to hostilities. Almost a thousand of these homes had electricity restored to them yesterday.

Since the beginning of a full-scale war with rf, energy workers have restored electricity to more than 615,000 households in the Dnipropetrovsk region. Some homes required restoration of electricity on multiple occasions due to frequent enemy attacks.

About 60 families remain without power.

If you have a power outage, please inform DTEK Dnipro Grids. We will do everything possible to promptly restore electricity. To contact the company please use official information channels only. Our specialists are ready to process your applications via remote service channels: website, social networks, contact center +38 (056/066/067/063) 790-99-00, 0-800-301-497, Viber and Telegram chatbots and Viber notification channel “ДТЕК info ДНЕМ”.

We are working 24/7 to ensure reliable power supply to houses and enterprises.

17 August 2026
Thermal power generation DTEK Grids DSO restored electricity to 900,000 homes in three regions over the course of the week
14 August 2026
Thermal power generation More than 2,700 green and distributed power generation facilities were connected over the course of six months, – DTEK Grids
13 August 2026
Thermal power generation 37 upgraded power facilities over six months: DTEK Grids DSO increased volumes of reconstruction and construction by 1.5 times
12 August 2026
Thermal power generation Energy workers of DTEK Dnipro Grids restored electricity to more than 26,000 families in the Dnipropetrovsk region over the course of two days
10 August 2026
Thermal power generation DTEK Grids DSO restored electricity to more than 1.2 mln homes in Donetsk, Odesa and Dnipropetrovsk regions over the course of the week
10 August 2026
Thermal power generation Electricity restored to almost 140,000 families in the Kyiv region: energy workers of DTEK Kyiv Regional Grids completed the restoration of the main grid after severe weather
07 August 2026
Thermal power generation In the first half of 2026, DTEK Grids DSO sent 777 tons of waste for recycling
05 August 2026
Thermal power generation The enemy attacked DTEK Dnipro Grids power facilities: 126,000 residents of the Dnipropetrovsk region were left without electricity
04 August 2026
Thermal power generation Over the course of six months, DTEK Grids DSO restored 240 power facilities, damaged during hostilities
03 August 2026
Thermal power generation From platforms for nests to GPS trackers: DTEK Dnipro Grids began live tracking of stork migration